Refineries and their structures are in an environment that is highly susceptible to deterioration. The processes for operation are often aggressive and ongoing, leading to structure deterioration.
A coker in the Gulf Coast had signs of deterioration after years of service producing and handling petroleum coke. The owner chose to implement an Investigate-Design-Build (IDB) approach for a seamless repair process that would allow the project to be completed within budget during an upcoming turnaround.
SIMCO Technologies performed a comprehensive condition assessment to characterize the extent aof deterioration, evaluate the condition of the coker structure, and develop an effective repair strategy to support its rehabilitation.
This was the first-of-its-kind project where ultra high-pressure (450ksi) water demolition was used to facilitate concrete removal, surface preparation, and cleaning of the reinforcing steel. Performed by STRUCTURAL, this method reduced this portion of the project from an anticipated 20 shifts with more than 20 employees to 6 shifts with only a few workers. This was a significant reduction in both time and safety exposure.
Following demolition of the existing concrete, the team performed concrete repairs throughout the coker structure, pit and maze.
The project was successful, giving the Owner fewer man-hours, an accelerated schedule, early turnover of the coker, completion under the original budget, and zero safety incidents.
Engineer: SIMCO
Contractor: STRUCTURAL